The Project
Hexley Interiors contacted us when they were tasked with creating a new office space for one of their clients Dunstan Thomas. The new building was in Portsmouth not far from their current office space, but with some of the furniture being moved across to the new building organisation was key to ensuring the project ran smoothly. WarrensOffice worked closely with Hexley throughout the project ensuring that the old and new furniture was correctly positioned on the plans, and that floor boxes were positioned correctly.
As the fit-out works neared completion, the team at Dunstan Thomas packed all their goods into crates to be transferred across to the new site, and our team of fitters arrived on Friday afternoon to start breaking everything down that needed to be moved across.
Services provided
Industry Sector
Business Services & Technology Solutions
Location
Lakeside, Building 3000, Portsmouth
Project year
2018
Project timeline
Removal of old furniture (1 day), Installation of new furniture (2 days)
Products supplied
Soft Seating, Lockers, Bench Desks (Fully Cable Managed), Desk Mounted Screens, Boardroom Table, Meeting Tables, Mesh Back Meeting Chairs
Installation profile
Removal of old furniture to be transferred to new site, Installation of new furniture & old furniture from previous site
Get in touch to start planning your new workspace today
Call, email, or fill in the form below and we will be happy to discuss your requirements in more detail, or arrange an initial site meeting.
Space planning, full colour renderings, sample products, fabric swatches, and mood boards are all available on request.